{"id":56583,"date":"2025-07-01T15:35:34","date_gmt":"2025-07-01T19:35:34","guid":{"rendered":"https:\/\/lakelandgazette.info\/news\/?p=56583"},"modified":"2025-07-01T15:35:41","modified_gmt":"2025-07-01T19:35:41","slug":"western-trunk-gravity-sewer-line-phase-one-construction-update","status":"publish","type":"post","link":"https:\/\/lakelandgazette.info\/news\/2025\/07\/01\/western-trunk-gravity-sewer-line-phase-one-construction-update\/","title":{"rendered":"WESTERN TRUNK GRAVITY SEWER LINE &#8211; PHASE ONE CONSTRUCTION UPDATE"},"content":{"rendered":"\n<p class=\"wp-block-paragraph\"><strong>LAKELAND, FL<\/strong>&nbsp;(July 1, 2025) &#8211; The City of Lakeland Water Utilities has launched Phase One of a critical infrastructure project to upgrade the Western Trunk Gravity Sewer Line. This major line, installed in the 1980s, carries approximately 3.5 million gallons of wastewater per day to the Southwest Pump Station through a 36-inch reinforced concrete pipe. Over time, structural lining and past repairs have reduced the pipe\u2019s diameter, limiting capacity and hindering system performance and future expansion.<\/p>\n\n\n<div class=\"wp-block-image\">\n<figure class=\"aligncenter size-large\"><img data-recalc-dims=\"1\" data-dominant-color=\"f0f0e5\" data-has-transparency=\"false\" style=\"--dominant-color: #f0f0e5;\" loading=\"lazy\" decoding=\"async\" width=\"1024\" height=\"529\" sizes=\"auto, (max-width: 1110px) 100vw, 1110px\" src=\"https:\/\/i0.wp.com\/lakelandgazette.info\/news\/wp-content\/uploads\/2025\/07\/Screenshot-2025-06-03-at-12.59.43-PM1-1024x529.webp?resize=1024%2C529&#038;ssl=1\" alt=\"\" class=\"wp-image-56584 not-transparent\" srcset=\"https:\/\/i0.wp.com\/lakelandgazette.info\/news\/wp-content\/uploads\/2025\/07\/Screenshot-2025-06-03-at-12.59.43-PM1-scaled.webp?resize=1024%2C529&amp;ssl=1 1024w, https:\/\/i0.wp.com\/lakelandgazette.info\/news\/wp-content\/uploads\/2025\/07\/Screenshot-2025-06-03-at-12.59.43-PM1-scaled.webp?resize=300%2C155&amp;ssl=1 300w, https:\/\/i0.wp.com\/lakelandgazette.info\/news\/wp-content\/uploads\/2025\/07\/Screenshot-2025-06-03-at-12.59.43-PM1-scaled.webp?resize=768%2C397&amp;ssl=1 768w, https:\/\/i0.wp.com\/lakelandgazette.info\/news\/wp-content\/uploads\/2025\/07\/Screenshot-2025-06-03-at-12.59.43-PM1-scaled.webp?resize=1536%2C793&amp;ssl=1 1536w, https:\/\/i0.wp.com\/lakelandgazette.info\/news\/wp-content\/uploads\/2025\/07\/Screenshot-2025-06-03-at-12.59.43-PM1-scaled.webp?resize=2048%2C1057&amp;ssl=1 2048w, https:\/\/i0.wp.com\/lakelandgazette.info\/news\/wp-content\/uploads\/2025\/07\/Screenshot-2025-06-03-at-12.59.43-PM1-scaled.webp?w=2220&amp;ssl=1 2220w\" \/><\/figure>\n<\/div>\n\n\n<p class=\"wp-block-paragraph\"><strong>Construction Area and Traffic Impacts<\/strong><\/p>\n\n\n\n<p class=\"wp-block-paragraph\">Phase One construction began in the Forrest Park and Lotus Avenue area, with traffic control measures currently in place. Digital message boards and standard traffic signage are being used to notify motorists and maintain public safety. Work will continue north along Lotus Avenue and is scheduled to cross Ariana Street during the week of July 7, 2025. &nbsp;This intersection will be closed for approximately three weeks, with clearly marked detours provided around the construction zone.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Phase One Scope<\/strong><br>Construction includes:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>A new 42-inch gravity\u00a0trunk\u00a0sewer line<\/li>\n\n\n\n<li>A new wastewater pump station<\/li>\n\n\n\n<li>24-inch and 30-inch force mains<\/li>\n\n\n\n<li>Collector lines and supporting infrastructure<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">This phase spans approximately&nbsp;12,800 linear feet&nbsp;of sewer main, with&nbsp;43 manholes&nbsp;and&nbsp;47 lateral connectionsdesigned to meet current and future wastewater demands.<\/p>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Why This Upgrade is Necessary<\/strong><\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Increased Capacity:<\/strong>\u00a0Supports community growth and eliminates system bottlenecks.<\/li>\n\n\n\n<li><strong>Public Safety:<\/strong>\u00a0Realigns sewer lines away from residential areas in the Oakhill, Colonial, and Citrus Center Colony Mobile Home Parks.<\/li>\n\n\n\n<li><strong>Harden Boulevard Improvements:<\/strong>\u00a01,400 linear feet of pipe will be rerouted from beneath Harden Blvd for better accessibility and safety.<\/li>\n\n\n\n<li><strong>Maintenance Access:<\/strong>\u00a0New infrastructure will improve inspection, maintenance, and emergency response efficiency.<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\"><strong>Public Notification &amp; Citizen Engagement<\/strong><br>The City of Lakeland is committed to transparent communication. Residents that may be directly impacted by the project will be notified through:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>Media notifications,\u00a0<a href=\"http:\/\/www.lakelandgov.net\/\" target=\"_blank\" rel=\"noreferrer noopener\">www.lakelandgov.net<\/a>, and social media<\/li>\n\n\n\n<li>Physical letters and door-to-door outreach<\/li>\n\n\n\n<li>Real-time alerts\u00a0via:<\/li>\n<\/ul>\n\n\n\n<ul class=\"wp-block-list\">\n<li><em>Everbridge<\/em>\u00a0text messaging (Water Utilities alert system)<\/li>\n\n\n\n<li><em>Voice-automated calls (reverse 911)<\/em><\/li>\n\n\n\n<li><em>Email notifications<\/em>\u00a0throughout each project phase<\/li>\n<\/ul>\n\n\n\n<p class=\"wp-block-paragraph\">For more information, please refer to the attached map or contact Guy Taylor at Lakeland Water Utilities at&nbsp;<a href=\"mailto:guy.taylor@lakelandgov.net\" target=\"_blank\" rel=\"noreferrer noopener\">guy.taylor@lakelandgov.net<\/a>.&nbsp;<\/p>\n","protected":false},"excerpt":{"rendered":"<p>LAKELAND, FL&nbsp;(July 1, 2025) &#8211; The City of Lakeland Water Utilities has launched Phase One of a critical infrastructure project to upgrade the Western Trunk Gravity Sewer Line. This major&hellip; <\/p>\n","protected":false},"author":2,"featured_media":56584,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_seopress_titles_title":"","_seopress_titles_desc":"","_seopress_robots_index":"","_seopress_robots_follow":"","_seopress_robots_imageindex":"","_seopress_robots_snippet":"","_seopress_robots_primary_cat":"12","_seopress_robots_breadcrumbs":"","_seopress_robots_freeze_modified_date":"","_seopress_robots_custom_modified_date":"","_seopress_robots_canonical":"","_seopress_social_fb_title":"","_seopress_social_fb_desc":"","_seopress_social_fb_img":"","_seopress_social_fb_img_attachment_id":0,"_seopress_social_fb_img_width":0,"_seopress_social_fb_img_height":0,"_seopress_social_twitter_title":"","_seopress_social_twitter_desc":"","_seopress_social_twitter_img":"","_seopress_social_twitter_img_attachment_id":0,"_seopress_social_twitter_img_width":0,"_seopress_social_twitter_img_height":0,"_seopress_redirections_value":"","_seopress_redirections_enabled":"","_seopress_redirections_enabled_regex":"","_seopress_redirections_logged_status":"","_seopress_redirections_param":"","_seopress_redirections_type":0,"_seopress_analysis_target_kw":"","inline_featured_image":false,"_uf_show_specific_survey":0,"_uf_disable_surveys":false,"wpai_generated_summary":"","footnotes":"","jetpack_publicize_message":"","jetpack_publicize_feature_enabled":true,"jetpack_social_post_already_shared":false,"jetpack_social_options":{"image_generator_settings":{"template":"highway","default_image_id":0,"enabled":true,"token":"eyJpbWciOiJodHRwczpcL1wvaTAud3AuY29tXC9sYWtlbGFuZGdhemV0dGUuaW5mb1wvbmV3c1wvd3AtY29udGVudFwvdXBsb2Fkc1wvMjAyNVwvMDdcL1NjcmVlbnNob3QtMjAyNS0wNi0wMy1hdC0xMi41OS40My1QTTEtc2NhbGVkLndlYnA_Zml0PTEwMjQlMkM1Mjkmc3NsPTEiLCJ0eHQiOiJXRVNURVJOIFRSVU5LIEdSQVZJVFkgU0VXRVIgTElORSAmIzgyMTE7IFBIQVNFIE9ORSBDT05TVFJVQ1RJT04gVVBEQVRFIiwidGVtcGxhdGUiOiJoaWdod2F5IiwiYmxvZ19pZCI6MTYzMDQwNjYxfQ.LptKT7mYSW1hWFo6Du6kFVuihZ9PmdcX1qvTp-JHpSoMQ"},"version":2,"attached_media":[{"id":56584,"url":"https:\/\/lakelandgazette.info\/news\/wp-content\/uploads\/2025\/07\/Screenshot-2025-06-03-at-12.59.43-PM1-scaled.webp","type":"image\/png"}]},"_wpas_customize_per_network":false},"categories":[12,14],"tags":[11765],"class_list":["post-56583","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-local","category-news","tag-western-trunk-gravity-sewer-line-phase-one-construction-update"],"jetpack_publicize_connections":[],"_links":{"self":[{"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/posts\/56583","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/comments?post=56583"}],"version-history":[{"count":1,"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/posts\/56583\/revisions"}],"predecessor-version":[{"id":56585,"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/posts\/56583\/revisions\/56585"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/media\/56584"}],"wp:attachment":[{"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/media?parent=56583"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/categories?post=56583"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/lakelandgazette.info\/news\/wp-json\/wp\/v2\/tags?post=56583"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}