A contractor working for the City of Lakeland will start a resurfacing project on January 23, 2023, that will take several weeks to complete. The project includes resurfacing 31 streets and is expected to be completed in early February 2023. The contractor will hang notices on resident doors along the impacted streets, at least two days before paving will start to notify them not to park on the street on their scheduled paving day. Traffic control will be in place on the impacted streets to assist motorists during the paving project.

The paving schedule is listed below. Due to weather and mechanical issues, the schedule could change slightly. Those residing on impacted streets will be notified by door hang tags and they will receive an SMS push notification.
January 23 January 27
Julie Lane Snowbird Avenue
Liberty Lane North Westgate Lane
Lamplighter Lane Chase Street
Dolly Lane Belmar Street
Benford Avenue
January 24 January 30
Rolling Woods Lane Luce Road
Bellview Avenue Hillman Lane
Windsor Street
Phillips Avenue
January 25 January 31
Jefferson Drive Aberdeen Court
Reany Road Lakeland Park Boulevard
Auburn Street Osceola Street
Alyce Street
Montgomery Avenue
Anderson Avenue
Bellgrove Street
January 26 February 1
Ricardo Lane 3rd Street
Tierra Alta Court Hunter Lane
Tierra Alta Drive
Meadowbrooke Avenue