PUBLIC NOTICE – PROJECT UPDATE FOR GRIFFIN ROAD SEWER MAIN REPLACEMENT

WHO:              Kamminga & Roodvoets, Inc.

WHAT:            Installation of 1,700 linear feet of 24-inch gravity sewer main

WHY:               Replacing older, failing infrastructure

WHEN:            Project is ongoing with an estimated late February 2024 completion

WHERE:           Griffin Road between Providence Road and Pyramid Parkway

Kamminga & Roodvoets, Inc. is installing approximately 1,700 linear feet of 24-inch gravity sewer main and 11 manholes along a portion of Griffin Road. The project is replacing older infrastructure along Griffin Road between Providence Road and Pyramid Parkway.  The project started in October 2023 and has an estimated February 29, 2024, completion date.  The contractor is working very quickly to complete this phase of the project and is in fact, ahead of schedule.  Once Kamminga & Roodvoets, Inc. has completed their portion of the project, Griffin Road will be repaved, and striped, and the sidewalk will be repaired. 

The existing gravity main is in service until wastewater can be routed to the new gravity sewer main when the project is completed. This ensures water/wastewater customers are not impacted by the construction of the new sewer main. Griffin Road is currently open for both east and westbound directions. Appropriate measures and detours are in place as part of a traffic management plan for the project.