Repairs to the CSX crossing and installation of new traffic signals are tentatively scheduled to begin on Tuesday 9/21/21 at County Line Road and US 92.)
The CSX railroad crossing is expected to be closed for a maximum of 14 days from the start of construction if repairs proceed as planned, pending any weather delays as well. Variable message boards have already been placed at the crossing and intersection alerting the public.

The City of Lakeland regrets any delays that may be experienced during this time, along with traffic disruption resulting from this closure. Due to longstanding statutory entitlements, CSX has considerable authority to close its crossings along public and private roadways. The City of Lakeland recognizes these repairs are necessary and will make for better, safer driving conditions when completed. To report a rail crossing issue or complaint, contact CSX at (877) 835-5279 or [email protected].
The new traffic signals (rebuild) is currently contracted for 220 days which puts completion of this portion, of the project in March 2022.