WHO: City of Lakeland Wastewater Division Contractor
WHAT: Robotic Investigation of Sewer Main
WHEN: Monday, January 6, 2025 – Monday, January 13, 2025
WHERE: Project will start at south end of the system and work north.
WHY: Inventory wastewater system for possible issues
Starting Monday, January 6, 2025, through Monday, January 13, 2025, including the weekend, a contractor working for the Wastewater Collection Division will conduct a robotic inspection of existing sewer mains in the areas marked in blue on the attached map. During this time, there may be temporary shoulder, sidewalk, and lane closures, with flaggers directing traffic. The contractor will begin at the southern end of the mapped area (near Glendale Street and New Jersey Road) and work northward toward the northern end (near Lake Hollingsworth Road and Frank Lloyd Wright Way) as the project progresses. This work involves the use of a robotic camera system inside existing sewer pipelines and does not require any excavation.